Grade Separation of Intersections on the Km 4 Ring Road, Sfax - Lot No. 2: RN13 and RN14 Intersections
The project aims to ease and secure traffic flow on the Km 4 ring road at the intersections with national roads RN13 and RN14. Two viaducts were built above these intersections to eliminate direct crossings between the traffic flows of the ring road and those of RN13 and RN14, thus allowing faster and safer vehicle movement from Tunis to Gabès (and vice versa).
Project details
Client:Ministry of Equipment and Territorial Planning
Location:Km 4 Ring Road, Sfax
Project end:2022
Amount:48,900,000 DT
Scope of work:
- Clearing of sites
- Earthworks
- Deep foundation works
- Sanitation and drainage works
- Construction of hydraulic structures under the ramps and under each roundabout
- Construction of two adjacent structures with continuous slab decks in reinforced concrete, each composed of three decks with a total length of 264 m
- Pavement works and roundabout development
- Public lighting, signaling, and safety equipment works