LEAR COPORATION - TCS

The Lear Corporation TCS project is a new, state-of-the-art production facility belonging to the American group Lear Corporation, a world leader in automotive equipment. Located in Menzel Bourguiba, this plant specializes in the manufacturing and assembly of Thermal Comfort Systems, including advanced heating, ventilation, and massage solutions for automotive seats. With a covered area of ​​32,050 m², the site incorporates high-precision infrastructure and specific technical installations to meet the most demanding technological standards of the global automotive industry.

project details
Client: Lear Corporation
Location: Menzel Bourguiba Bizerte, Tunisia
End of project: 2025
Amount:100 910 000 DT
Scope of work:
  • This project, which represents a major expansion of the group's production capacity, was carried out by SBF as a turnkey project, comprising the following packages:
  • - Civil Engineering & Finishing Works: Structural works including high-precision infrastructure, a structure combining a prefabricated concrete frame and a steel frame, as well as the installation of hollow-core slabs. This package also includes a reinforced industrial slab to support the production lines for electronic and thermal components.
  • - Fluids & Process: Installation of specialized plumbing systems, as well as high-performance heating, ventilation, and air conditioning (HVAC) solutions
  • - Electricity & Intelligent Systems: Implementation of a complete electrical infrastructure (high/low voltage power supply, lighting) and advanced security systems. This package covers the specific energy requirements for test benches and electronic assembly units.
  • - Fire Safety (Sprinkler): Installation of an automatic fire suppression system of the Sprinkler type covering the entire 32,050 m², guaranteeing optimal protection of personnel and high-tech equipment.
Project specifics :
  • a large-scale industrial project, completed within ambitious deadlines, incorporating advanced construction technologies and complying with the strict standards of the automotive industry
project duration: 16 Months

Let's build the future project by project

Projects

Stade Olympique
OLYMPIC STADIUM
The largest stadium in Tunisia, with 60,000 seats; SBF produced the entire supporting structure of the stadium, consisting of 64 gantries with a height of 33 metres.
Read more
Banque Tuniso-Lybienne
Tunisian-Libyan Bank
SBF completed the construction of the office building for the headquarters of Banque Tuniso-Libyenne BTL.
Read more
Musee-national
National Museum
This project is located on the site of the National Museum of Bardo, mainly includes two construction sites which were carried out in parallel and which are
Read more
Clinique-Amen
Amen Clinic
This project consists of a basement, ground floor and 6 floors, it was completed on time and in accordance with the objectives of the project owner.
Read more
Village de Transit
Transit Village
Construction of a village of Arab-Muslim architecture on a total surface area of 11,500 m2, including 9,500 m2 of covered areas.
Read more
Azur city
Azur city
An ambitious architectural work On the banks of the suburbs, the SBF team carried out the major works of the main commercial and leisure center in Tunisia
Read more
Tunis City
Tunis City
SBF, the successful bidder for the “Structures” lot of the project (with a deadline of 10 months), proposed and implemented, as a replacement for the traditional solution
Read more
unité d'acide phosphorique
phosphoric acid unit
The M’dhila project of the new 54% concentrated phosphoric acid production plant with a view to producing triple super phosphate at the existing M’dhila plant