The project consists of constructing a compression unit, renewing five existing units, and the general redevelopment of a gas pumping station to ensure the continuous transport of Algerian gas to Italy via subsea pipelines.
project details
Client:Scogat - Snamprogetti
Location:Haouaria, Nabeul
Project completion:2007
Amount:3,000,000 DT
Scope of work:
- Construction of reinforced concrete works for the foundations of the compression units.
- Construction of pipe supports (pipe racks) with metal frameworks.
- Earthworks for pipelines and underground networks.
- Installation of electrical and control cables.
- Exterior landscaping works.
Project specifics:
The complexity of the project lies in the fact that all work was carried out while keeping the station fully operational during the 11 months of construction. This required extreme vigilance and strict coordination.
Let's build the future project by project
Projects
OLYMPIC STADIUM
The largest stadium in Tunisia, with 60,000 seats; SBF produced the entire supporting structure of the stadium, consisting of 64 gantries with a height of 33 metres.
This project is located on the site of the National Museum of Bardo, mainly includes two construction sites which were carried out in parallel and which are
An ambitious architectural work On the banks of the suburbs, the SBF team carried out the major works of the main commercial and leisure center in Tunisia
SBF, the successful bidder for the “Structures” lot of the project (with a deadline of 10 months), proposed and implemented, as a replacement for the traditional solution
The M’dhila project of the new 54% concentrated phosphoric acid production plant with a view to producing triple super phosphate at the existing M’dhila plant