Construction of the STELIA Industrial Unit

Description of the work

Construction of the STELIA Industrial Unit

The project involves the construction of a new industrial unit for STELIA Aerospace in El Mghira, Ben Arous. This factory will be dedicated to the manufacture of components and equipment for aircraft cabins.

Project Details

Client: AIRBUS ATLANTIC TUNISIA

Project Completion: 2023

Location: Z.I El Mghira, Ben Arous

Amount: 12 000 000 DT

Scope of work:

  • Area: 10,000 m²
  • Reinforced concrete work for foundations and walls
  • Masonry and plastering work
  • Suspended ceiling and Placoplatre work
  • Aluminium joinery work
  • waterproofing work
  • Painting work
  • Road and utility works

Let's build the future project by project

Projects

Olympic Stadium

The largest stadium in Tunisia, with a capacity of 60,000; SBF constructed the entire load-bearing structure of the stadium, consisting of 64 portals, each 33 meters high.

Tunisian-Libyan Bank

SBF carried out the construction of the office building for the headquarters of the Tunisian-Libyan Bank BTL.

National Museum

The present project is located on the grounds of the Bardo National Museum, and mainly comprises two construction sites that were carried out in parallel and which are

Amen Clinic

This project consists of a basement, ground floor and 6 floors, it was completed on schedule and in accordance with the client’s objectives.

Transit Village

Construction of a village of Arab-Muslim architecture on a total area of ​​11,500 m2, of which 9,500 m2 are covered areas.

Azur City

An ambitious architectural project: On the banks of the suburbs, the SBF team carried out the structural work for the main commercial and leisure center in Tunisia.

Tunis City

SBF, the successful bidder for the “Structures” package of the project (with a 10-month deadline), proposed and implemented, as a replacement for the traditional solution

phosphoric acid unit

The M’dhila2 project involves a new 54% concentrated phosphoric acid production plant, with the aim of producing triple superphosphate at the existing M’dhila1 plant.