Société Bouzguenda Frères

Project

ASBU HOTEL AND BUSINESS CENTER

Description of the work

ASBU HOTEL AND BUSINESS CENTER

The project consists of the construction of a 5* luxury hotel and a business center in the North Urban Center of Tunis, comprising a basement and 9 floors.

Project Details

Client: ARAB STATES BROADCASTING UNION – ASBU

Project Completion: 2019

Location: North Urban Center, Tunis

Amount: 15 000 000 DT

Scope of work:

  • Area: 10,000 m²
  • Foundation work
  • Reinforced concrete works (including prestressed concrete slabs)
  • Masonry work
  • waterproofing work
  • Exterior cladding and facade work
  • Interior renovation work
  • Interior and exterior carpentry work
  • Painting and wall covering work (especially those with Bissaza gold leaf)
  • Site development and infrastructure works (access roads, various networks, landscaping)

Project Specificities:

  • The project is distinguished by the use of post-tensioned prestressed concrete slabs.

Let's build the future project by project

Projects

Olympic Stadium

The largest stadium in Tunisia, with a capacity of 60,000; SBF constructed the entire load-bearing structure of the stadium, consisting of 64 portals, each 33 meters high.

Tunisian-Libyan Bank

SBF carried out the construction of the office building for the headquarters of the Tunisian-Libyan Bank BTL.

National Museum

The present project is located on the grounds of the Bardo National Museum, and mainly comprises two construction sites that were carried out in parallel and which are

Amen Clinic

This project consists of a basement, ground floor and 6 floors, it was completed on schedule and in accordance with the client’s objectives.

Transit Village

Construction of a village of Arab-Muslim architecture on a total area of ​​11,500 m2, of which 9,500 m2 are covered areas.

Azur City

An ambitious architectural project: On the banks of the suburbs, the SBF team carried out the structural work for the main commercial and leisure center in Tunisia.

Tunis City

SBF, the successful bidder for the “Structures” package of the project (with a 10-month deadline), proposed and implemented, as a replacement for the traditional solution

phosphoric acid unit

The M’dhila2 project involves a new 54% concentrated phosphoric acid production plant, with the aim of producing triple superphosphate at the existing M’dhila1 plant.