Description

The works (construction of a compression unit, renewal of 5 others and refurbishment of the station) were carried out within 11 months and in an extremely vigilant environment as the station continued to operate normally in order to ensure the transport of Algerian gas towards Italy through submarine pipelines via the Sicily channel.
Achieved work (in accordance with international standards and the Quality plans and HSE elaborated by SBF and approved by the Client): reinforced concrete works for the foundations of compression units, pipe racks in metal frame, pipe earthworks and buried networks, installation of cables and outdoor fittings.

Project details

Categories:
Client: Scogat - Snamprogetti
Location: Bizerta raoud - Tunisia
Completed: January 2007
Value: 2,943,000 TND