The project consists in carrying out the civil works of the combined-cycle power plant in Radès C, 1 x 450 mw:
- Execution of the gas turbine works.
- Execution of the steam turbine works.
- Execution of the pumping station / Shielding work on slurry wall.
- Execution of technical, administrative, electrical buildings.
- Concrete quantity: 25,000 m3
- Steel: 4,300 Tons.
- Sheet pile works: 14,500 m2.
- Laying of 600 mL of BONNA Concrete pipes with diameters of 2,000 and 2,800.
- Pipe sinking of concrete pipes with a diameter of 2,000.
- Roads and infrastructure works / 6,000 m2 of asphalt